Options compared
The project next to doing nothing, side by side. Change any number and everything recalculates.
Options
Gulf Breeze Highway 98 utility undergrounding (CRA-financed)
Santa Rosa County · published and derived values; assumptions are labelled
Alternatives
Time horizon
Candidate route and service density
Assumptions — Underground US 98 (as built)
Capital, operations and demand
Gulf Breeze CRA tax increment (county + city)
Lifecycle outlook
Break-even calculation
Net value to the owner, by years looked at
−$6.8M whether you look 20, 40 or 60 years ahead: the project brings the owner no income, so its cost to the owner does not change with the years counted.
Each option compared with doing nothing
| Alternative | Capital | Net value to owner | Benefit ÷ cost |
|---|---|---|---|
| Underground US 98 (as built) | $7.2M | −$6.8M | Not measured |
The owner’s cash is discounted at 4.8% a year in nominal dollars; the benefit-cost ratio at 7.0% in real dollars.
Open loan and repaymentScreening only, not engineering design. No implied connection approval